Update on Playground Build at Center Woods
Prior to the build days we need to remove sand from both playgrounds.
On Friday, the major task will be digging holes for the equipment. These holes will need either brick or concrete slabs in the bottom to anchor the equipment. If you have any bricks or blocks you could donate, please contact Marybeth Pike at marybethpike@wearefriendspto.com. The base poles of the equipment will be assembled and put in the holes. We need some backhoes with an auger attachment to make this part go smoothly.
On Saturday, the bulk of the equipment will be assembled and put on the anchors. Late in the day, the concrete will be poured around the structures.
On Sunday, the wood carpet will be spread. We will need backhoes to get this done quickly.
Once constructed, we will not be able to use the playground for another 3-4 days while the concrete sets.
If you are able to volunteer some time to help with the construction of the new playground, please contact Sharon Fudala at: